VB Quang Yen Industrial Park is located in Phong Coc Ward (formerly Quang Yen Town), Quang Ninh Province (within the Quang Yen Coastal Economic Zone).

Boundaries and inter-regional connectivity of the VB Quang Yen Industrial Park, Quang Ninh
The VB Quang Yen Industrial Park is located in Phong Coc Ward (formerly Quang Yen Town), Quang Ninh Province (within the Quang Yen Coastal Economic Zone), specifically:
– North: Borders existing aquaculture land and protection forest;
– South: Borders the Ha Long – Hai Phong Expressway;
– East: Borders existing aquaculture land, protection forest, and frontage roads;
– West: Borders the Bach Dang River.

Target sectors
Infrastructure of VB Quang Yen Industrial Park, Quang Ninh
**Water Supply System**
The total water supply demand for the industrial park is estimated at approximately 24,000 m³/day, comprising 15,000 m³/day for Phase 1 and an additional 9,000 m³/day for Phase 2.
**Power Supply System**
Management of the medium-voltage power supply system, transformer stations, electrical cabinets, and lighting for roads and public facilities within the industrial park.
**Wastewater Treatment System**
Collection of wastewater from land plots, service areas, and secondary factories to the centralized wastewater treatment plant; operation of the centralized treatment plant with a total capacity of approximately 15,000 m³/day (9,000 m³/day for Phase 1 and an additional 6,000 m³/day for Phase 2).
**Telecommunications System**
Installation of telecommunications infrastructure, including communication cables, technical conduits, technical manholes, technical cabinets, and other components to facilitate connectivity, data transmission, and industrial park operations management.
Legal Status of VB Quang Yen Industrial Park, Quang Ninh
Decision No. 335/QĐ-BQLKKT, dated June 28, 2026, issued by the Management Board of Quang Ninh Economic Zones, approving the investment policy and the investor for the VB Quang Yen Industrial Park project.
Implementation Schedule for VB Quang Yen Industrial Park, Quang Ninh
– According to the plan, the project is expected to complete master planning, the Environmental Impact Assessment (EIA), land conversion, site preparation, and land leveling between Q3 2026 and Q1 2027.
– Q1 2027 – Q4 2027: Construction of facilities.
– Q3 2028 – Q4 2028: Completion of comprehensive infrastructure and commencement of operations.
Developer Information for VB Quang Yen Industrial Park, Quang Ninh
The project developer is VB Nha Mac Joint Stock Company, established on May 14, 2026, with a charter capital of VND 590 billion. The company has three shareholders: VB Holdings JSC (60%), Vu Ngoc Anh (25%), and Director Do Van Binh (15%). Its headquarters is located at Ngoc Chau Port Urban Area, Tuan Chau Ward, Quang Ninh Province.
Quick Facts: VB Quang Yen Industrial Park, Quang Ninh
Source: https://cafeland.vn/